Project:Mechanical

Xstrata

BESTECH was involved in the complete re-design of the client’s smelter process water pump house and booster pump house.

This included the installation of two priming pumps and six VFD-controlled 350-hp primary pumps. It also involved the complete re-design and installation of the power distribution system. BESTECH completed the programmable logic controller (PLC) and human-machine interface (HMI) programming and led the commissioning and construction management.